Challenge To mitigate a $5 million claim for differing site conditions filed in the U.S. District Court, Western District of Kentucky at Louisville, against the Louisville Metro Sewer District by the prime contractor on a wastewater/sewer project.
Solution

PMT staff, under the direction of the lead attorney for Pedley Zielke & Gordinier, performed a collapsible as-built schedule analysis of the delay issues associated with the construction of this project.
PMT staff provided analyses utilized during a bench trial, mitigating a $5-million, third party indemnification claim filed against the Louisville Metro Sewer District by the prime contractor, down to a $339,000 judgment in favor of the prime contractor.

 

 