PMT provided CPM scheduling services to Van Winkle
to develop the project schedule. PMT worked with Van
Winkle project managers to develop overall project milestones
and requirements. PMT meet with each subcontractor to
detail specific, tasks, durations, constraints, relationships
and resource requirements. PMT and Van Winkle reviewed
the project drawings and specifications to determine
optimal project sequencing and logistics. PMT developed
the schedule using Primavera Project Planner (P3), the
integrated project schedule was accepted by the owner
with minimal comments. PMT provided monthly schedule
updates and status reports enabling management to make
informed decisions based on up to date information.
PMT was able to develop a detailed CPM schedule which
enabled the project to be completed on-time and on-budget
while incorporating an 20% scope increase from owner
change orders.
|